Buran Orbiter Construction and Flight Milestones
9 rows × 2 cols · edited 12 days ago, 15 November 2026
Buran was a Soviet spaceplane designed to launch into orbit aboard the Energia rocket and return to Earth. Its development involved a long process of assembly, testing, and preparation across Soviet facilities.
The milestones trace the first orbiter’s progress from the start of assembly to its uncrewed orbital flight.
| Date | Milestone |
|---|---|
| 1980 | Assembly started |
| August 1983 | Fuselage delivery to NPO Energia |
| March 1984 | Start of comprehensive electrical testing |
| December 1984 | Delivery to Baikonur |
| April 1986 | Start of final assembly |
| 15 November 1987 | Final assembly completed |
| 15 November 1987 – 15 February 1988 | Testing in MIK OK |
| 19 May – 10 June 1988 | Test rollout |
| 15 November 1988 | Orbital flight (1K1) |
Source: en.wikipedia.org/wiki/Buran_(spacecraft), shared under CC BY-SA 4.0.