Buran Orbiter Construction and Flight Milestones

9 rows × 2 cols · edited 12 days ago, 15 November 2026

Buran was a Soviet spaceplane designed to launch into orbit aboard the Energia rocket and return to Earth. Its development involved a long process of assembly, testing, and preparation across Soviet facilities.

The milestones trace the first orbiter’s progress from the start of assembly to its uncrewed orbital flight.

DateMilestone
1980Assembly started
August 1983Fuselage delivery to NPO Energia
March 1984Start of comprehensive electrical testing
December 1984Delivery to Baikonur
April 1986Start of final assembly
15 November 1987Final assembly completed
15 November 1987 – 15 February 1988Testing in MIK OK
19 May – 10 June 1988Test rollout
15 November 1988Orbital flight (1K1)

Source: en.wikipedia.org/wiki/Buran_(spacecraft), shared under CC BY-SA 4.0.